VIII

Restarts, uprates & nuclear utilities

Existing gigawatts are the only nuclear that ships this decade; restarts, uprates and datacenter PPAs carry dated public catalysts.

Who owns it

The gigawatts that ship this decade already exist. New large-scale nuclear in the US is a 2032+ story, and most SMR designs are unbuilt and unlicensed, so the only nuclear capacity that can serve datacenter load before 2030 is the operating fleet plus a thin pipeline of restarts and uprates. That makes the merchant-leaning nuclear owners the clearest expression of this chokepoint. Constellation (NASDAQ: CEG) owns the largest such restart: the 835 MW former Three Mile Island Unit 1, rebranded the Crane Clean Energy Center, under a 20-year PPA with Microsoft, with the in-service target pulled forward to 2027. Constellation layered on a 20-year, 1,121 MW Clinton PPA with Meta plus a 30 MW uprate. Talen Energy (NASDAQ: TLN) expanded its Amazon relationship to 1,920 MW from Susquehanna through 2042, worth up to ~$1.4B in annual revenue at full ramp. Vistra (NYSE: VST) signed a 1,200 MW Comanche Peak PPA with AWS and ~2,609 MW of Meta PJM nuclear PPAs that bundle 213/80/140 MW uprates at Perry, Davis-Besse and Beaver Valley. NextEra (NYSE: NEE) is restarting the 615 MW Duane Arnold plant under a 25-year Google PPA.

What breaks it

The constraint is physical and regulatory, not commercial. A restart is a multi-year, capital-heavy NRC proceeding: Crane runs through a dedicated NRC Restart Panel with a final decision expected in 2027, and Duane Arnold's restart hinges on NRC approval with first power not expected until early 2029 at a cost above $1.6B. Uprates are slower still: Vistra's PJM uprate energy does not begin delivery until ~2031, ramping to 2034. PPA headline MW also overstate near-term cash: Talen's full 1,920 MW is not delivered until 2032, and Vistra's AWS power ramps to full capacity by 2032. The fleet is finite — there are only a handful of restartable units and limited uprate headroom — so the chokepoint is the absence of incremental electrons, not demand.

What forces the reprice

The catalyst tape is the NRC docket and dated PPA milestones, not conference vibes. Discrete reprice events include the NRC's Crane draft EA/FONSI (issued early June 2026, comment period closing July 8) and the final EA/FONSI expected September 2026, moving toward a 2027 restart decision; Crane and Duane Arnold synchronization dates; uprate construction starts; and each new signed offtake. Earnings are amplifiers: Constellation's nuclear production tax credit provides an inflation-linked floor under the whole fleet, and management affirmed FY2026 adjusted operating EPS guidance of $11.00-$12.00 after the $16B Calpine close. Vistra posted record Q1 2026 adjusted EBITDA of $1.494B with ~3.2 GW of nuclear still uncontracted — every GW it places under a hyperscaler PPA converts merchant exposure into 20-year cash.

Be honest about size and earliness

Unlike the SMR developers, these names have real revenue today — but the datacenter-nuclear narrative is mostly future cash flow. Talen's 1,920 MW deal generates up to ~$1.4B annual revenue only once fully ramped by 2032; today it is a refueling-outage transition to front-of-the-meter delivery. Crane (2027) and Duane Arnold (2029) contribute zero electrons until those dates and remain contingent on NRC sign-off. Vistra's uprate megawatts are a 2031-2034 story. So the right framing: CEG, VST and TLN are operating-fleet cash machines (PTC-floored, hedged) onto which a multi-year restart/uprate growth option is bolted — the option, not current EBITDA, is what the datacenter PPAs price. Be especially disciplined on the SMR-adjacent language in these deals: Talen and AWS only agreed to explore SMRs and uprates, which is an MOU, not an order. NEE's restart is genuine but the holdco is a regulated-utility-plus-renewables giant where one 615 MW unit barely moves consolidated earnings — it is a sentiment and optionality story, not a needle-mover. PSEG (NYSE: PEG) belongs on the watchlist precisely because its nuclear-to-datacenter exposure is still exploratory talks and a Salem uprate, with no signed nuclear offtake. Distinguish signed PPAs (CEG/Microsoft, CEG/Meta, VST/AWS, VST/Meta, TLN/Amazon, NEE/Google) from everything else, every time. This is structure and catalysts, not advice.

Who owns the choke

CEGcore

Constellation Energy Corporation

$265.39-1.7%

Restarting the 835 MW former Three Mile Island Unit 1 (Crane Clean Energy Center) under a 20-year Microsoft PPA, target accelerated to 2027 with an NRC restart decision expected in 2027. Separately signed a 20-year, 1,121 MW Clinton PPA with Meta including a 30 MW uprate (full uprate ~2029). Q1 2026 adjusted operating EPS $2.74; FY2026 guidance $11.00-$12.00.

Bull
Constellation owns the largest restart, the 835 MW Crane center, plus a 1,121 MW Clinton PPA, both 20-year hyperscaler contracts bolted onto a PTC-floored operating fleet.
Bear
Crane delivers zero electrons until 2027 and remains contingent on an NRC restart decision, so the growth option carries multi-year regulatory and execution risk.

[1] [2] [3]

NEEwatch

NextEra Energy, Inc.

$90.37+1.7%

Restarting the 615 MW Duane Arnold Energy Center in Iowa under a 25-year Google PPA, targeting return to service by early 2029 at a cost above $1.6B; NRC approved the transfer of the remaining 30% ownership and FERC granted a required waiver. Restart remains pending full NRC restart approval.

Bull
NextEra is restarting the 615 MW Duane Arnold plant under a 25-year Google PPA with NRC ownership transfer and FERC waiver secured, adding restart optionality to a utility giant.
Bear
One 615 MW unit barely moves a regulated-utility-plus-renewables giant, and the restart still hinges on pending full NRC approval before any 2029 power flows.

[1] [2]

PEGwatch

Public Service Enterprise Group Incorporated

$80.43+1.5%

PSEG owns the Salem (~2.3 GW) and Hope Creek nuclear units on Artificial Island and has confirmed exploratory talks to sell nuclear power to datacenters (front- and behind-the-meter); its large-load pipeline has surged to ~9.4 GW (~90% datacenters) and it plans a ~200 MW Salem uprate in 2027-2029. No signed nuclear offtake to date.

Bull
PSEG owns ~2.3 GW Salem plus Hope Creek, a ~9.4 GW large-load pipeline that is ~90% datacenters, and a planned ~200 MW Salem uprate for 2027-2029, with talks underway.
Bear
PSEG has no signed nuclear offtake to date and only exploratory datacenter talks, so its chokepoint exposure is the least-converted among the restart utilities.

[1] [2]

TLNcore

Talen Energy Corporation

$322.99-6.9%

Expanded its Amazon relationship in June 2025 to a 1,920 MW PPA from the Susquehanna nuclear plant through 2042, expected to generate up to ~$1.4B in annual revenue at full ramp (full delivery ~2032), moving to a front-of-the-meter model after the Spring 2026 refueling outage. Talen and AWS will separately explore new SMRs and uprates (non-binding).

Bull
Talen's 1,920 MW Susquehanna PPA with Amazon runs to 2042 and could generate ~$1.4B annual revenue at full ramp, layering a hyperscaler growth option onto an operating-fleet cash machine.
Bear
Full 1,920 MW delivery is not until ~2032, the SMR/uprate work is only a non-binding exploration MOU, and near-term cash trails the headline figure.

[1] [2]

VSTcore

Vistra Corp.

$149.86-4.6%

Signed a 20-year, 1,200 MW Comanche Peak PPA with AWS (delivery from Q4 2027, full by 2032) and ~2,609 MW of 20-year Meta PJM nuclear PPAs including 213 MW (Perry), 80 MW (Davis-Besse) and 140 MW (Beaver Valley) of uprate capacity, with uprate delivery 2031-2034. Q1 2026 record adjusted EBITDA $1.494B with ~3.2 GW nuclear uncontracted.

Bull
Vistra signed a 1,200 MW Comanche Peak AWS PPA plus ~2,609 MW of Meta nuclear PPAs with uprates, posting record $1.494B Q1 EBITDA with ~3.2 GW nuclear still uncontracted to place.
Bear
AWS power ramps to full only by 2032 and uprate megawatts deliver 2031-2034, so the hyperscaler growth option is well ahead of the cash.

[1] [2]

Catalyst calendar

  • 2027-01-01NRC final decision on Crane Clean Energy Center restart (expected 2027)highNRC review of the Crane Clean Energy Center (ex-Three Mile Island Unit 1) restart is the gating regulatory step before Constellation returns the unit to service for its Microsoft PPA; a final decision is expected in 2027 (date is a placeholder).
  • 2026-07-29NextEra Energy Q2 2026 earningsmediumThe print is the venue for any update on the Duane Arnold restart timeline and NRC progress that underpins its restart optionality.
  • 2026-07-30Constellation Energy Q2 2026 earningsmediumUpdates on Crane restart spend/schedule, Clinton uprate progress and PTC-floored fleet economics drive the restart-and-uprate reprice.
  • 2026-08-06Talen Energy Q2 2026 earningsmediumFirst print after the Spring 2026 Susquehanna outage and front-of-the-meter transition tied to the 1,920 MW Amazon PPA ramp.

View these names in the dashboard →