Catalyst calendar

The repricing schedule is mostly public if you actually look at it.

High-impact · next 30 days

  • 2026-09-30NRC final Environmental Impact Statement for GLE's Paducah Laser Enrichment Facility

September 2026

  • 30highPolicyNRC final Environmental Impact Statement for GLE's Paducah Laser Enrichment FacilityCompleting the EIS (NRC-targeted Sept 2026) is a gating regulatory step toward licensing the only Western laser-enrichment plant, de-risking the longer-dated disruption of the SWU chokepoint for Silex and Cameco.

January 2027

  • 31highPolicyNRC Safety Evaluation Report for GLE Paducah facility (anticipated)The SER is the safety-side prerequisite to an NRC construction-and-operation license for laser enrichment; its completion would clear the path to a build decision on a second-source enrichment technology.

January 2028

  • 01highPolicyRussian LEU import waivers terminate (Prohibiting Russian Uranium Imports Act)Hard statutory date after which no Russian-uranium import waivers can be granted, forcing Western utilities onto a constrained non-Russian SWU base and directly tightening the enrichment chokepoint.

Past

  • 2026-08-04Centrus Energy Q2 2026 earnings